Xylem provides temporary bypass at Denver treatment plant

USA

In Colorado, the project team for an expansion and renovation of a wastewater treatment plant was in need of a bypass system to move a peak flow of 128 million gallons per day. Wagner Rents, the rental arm of Wagner Equipment and Xylem’s Godwin and Flygt distributor in Colorado was named the bypass contractor for this portion of the job. Wagner Rents pump team worked with Xylem to design and install a temporary system to convey the full amount of flow. The solution that followed also provided the treatment plant with the ability to integrate the temporary bypass into its SCADA system and to log the data as if it was its own permanent pumping system.